To find out more about the project, please view some of our Frequently Asked Questions, or contact us at melrosetriangle@gmail.com.
Market conditions do not permit the approved project to move forward at this time. The Charles Company in conjunction with the City of West Hollywood are looking to secure the site for neighbors and pedestrians in the area.
It is anticipated that it will take between 6- 9 months to fill the hole depending on weather conditions and availability of fill materials. Regular updates on the progress of the work can be found on this website.
No street closures are planned at this time. Should circumstances require a street closure, notification will be provided in advance.
All work will be done during the city’s permitted construction hours: Monday through Friday, 8 a.m. - 7 p.m. and Saturdays, 8 a.m. - 7 p.m. If the need arises to seek an extended hours construction permit, notification will be provided in advance to the community and interested stakeholders.
Yes, there will be 3 community meetings held on [DATE] at Xam, Xpm, and Xpm to provide community members with an overview of the construction process and contact information to ask questions and express concerns. More information and a Zoom link will be provided.
Once the hole is filled and secured, the uses on site will be consistent with City regulations. The Charles Company will continue to work with the City to ensure that appropriate public safety measures are implemented.
The future of the property has not yet been determined, and any plans will be subject to City approvals and robust stakeholder/community engagement.